Simple payback for energy savings
According to approved document L of the building regulations, in relation to the conservation of fuel and power, the term 'simple payback' refers to:
The amount of time it will take to recover an initial investment through energy savings, calculated by dividing the marginal additional cost of implementing an energy efficiency measure by the value of the annual energy savings achieved by that measure taking no account of VAT.
When making this calculation, the following guidance should be used:
- The marginal additional cost is the additional cost (materials and labour) of incorporating, for example, additional insulation, not the whole cost of the work.
- The cost of implementing the measure should be based on prices current at the date the proposals are made known to the building control body (BCB) and be confirmed in a report signed by a suitably qualified person.
- The annual energy savings should be estimated using an energy calculation tool approved by the Secretary of State pursuant to regulation 24.
- For the purposes of the approved document, the energy prices that are current at the time of the application to building control should be used when evaluating the annual energy savings. Current energy prices can be obtained from the Department of Energy & Climate Change (DECC) website.
Typically, an initial investment, in for example the achievement of U-values, will be considered economically feasilbe if the simple payback period is not greater than 15 years. However, other periods may be considered economically feasible for other elements.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
New project and cultural district described in detail.
The nature of EPCs, crticism and inaccuracies.
History, issues and redesign.
From waste recycling to energy performance the hierchy.
An introduction to WERCS and WEEE responsibilities
Dealing with 2 million tonnes of waste equipment a year.
Global BACS Market: analytics and optimisation
A BSRIA glance at building automation and control systems.
What it is and how to use it.
Types of insulating plaster by binder and insulant.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.